NPV Function
Calculates what a series of future cash flows is worth today.
Category
Financial
Available in
All versions, Microsoft 365
Returns
A net present value
Overview
NPV discounts future cash flows back to today at a chosen rate (your cost of capital). A positive result after subtracting the up-front cost means the project earns more than that rate.
The catch: NPV assumes the first value arrives one period from now. An investment made today must be added outside the function, not included in it.
Syntax
Arguments
| Argument | Required? | What it does |
|---|---|---|
| rate | Yes | The discount rate per period. |
| value1, value2, … | Yes | Cash flows, one per period, in order — as ranges or values. |
Examples
Example 1 — Should Northstar open the new store?
The fit-out costs $150,000 today and is expected to return four years of cash. Northstar's cost of capital is 8%.
| A | B | |
|---|---|---|
| 1 | Year | Cash flow |
| 2 | 0 (today) | -$150,000 |
| 3 | 1 | $40,000 |
| 4 | 2 | $50,000 |
| 5 | 3 | $60,000 |
| 6 | 4 | $55,000 |
| 7 | NPV | $17,960.55 |
Positive, so the store beats an 8% return by about $18,000 in today's money.
Example 2 — The classic mistake
Including today's $150,000 inside NPV discounts it by a year, as if it were spent in year 1.
| A | B | |
|---|---|---|
| 1 | Formula | Result |
| 2 | Wrong: cost inside NPV | $16,630.14 |
| 3 | Right: cost added after | $17,960.55 |
Common mistakes
- NPV is understated. The time-0 investment was put inside the function. Add it separately.
- Irregular dates. NPV assumes equal spacing. Use XNPV when cash arrives on specific dates.